Mode of Implementation Three Phases on a Turnkey Basis.

Rural Bridges Project-Phase-1(210 Nos)



uPhase-1 Project was Completed by former Ministry of 
Economic Development.

    Rural Bridges Project-Phase-II(537 Nos)
uScope of Work: :-Design and build of 537 Nos of bridges. Width 5.5 Meters and span is  ranging from 6 Meters to 30 Meters.
uProject Cost             :-  GBP 100 mn
uSource of Funds      :-  ECGD, /Deutsche
uMain Contractor     :-  M/S. Cleveland Bridge Uk Ltd.
uEffective Date          :-  09-12-2014
uCompletion Date    :-  08-12-2017
Rural Bridges Project-Phase-III(463 Nos)
uScope of Work   :- Design and build of 463 Nos of bridges. Width 5.5 Meters and span is  ranging from 6 Meters to 30 Meters.
uProject Cost             :-  Euro 105 mn
uSource of Funds      :-  ATRADIUS/Netherland/Rabobank
uMain Contractor     :-  M/S. Janson Bridging International,BV
uEffective Date          :-  31-12-2014
uCompletion Date    :-  30-12-2017








































Comments

Popular posts from this blog

Pudukudi iruppu bridge - 1486 Thampalagamam PS

  Date Handed Over 30.06.2017 Agency      Thampalagamam PS After Before

Stages of Construction and Implementing Mechanism

Stages of Construction and Implementing Mechanism Mile Stone-1 :-Mobilization, Soil Testing, Base Construction . Mile Stone-2 :-Construction of abutments, Capping Beams and Wing Walls Mile Stone-3 :-Erection Steel Deck, Bearing Pad, Assembling work, any Extra                           works Mile Stone-4 :- Concrete Deck, Guard Stones, Expansion Joints, Approach Roads.

GaloyaWeeragoda Udayapura Rajamaha Vihara - 1715 Uhana PS

       Date Handed Over      20.11.2017      Agency          Uhana PS     After      Before