Mode of Implementation Three Phases on a Turnkey Basis.

Rural Bridges Project-Phase-1(210 Nos)



uPhase-1 Project was Completed by former Ministry of 
Economic Development.

    Rural Bridges Project-Phase-II(537 Nos)
uScope of Work: :-Design and build of 537 Nos of bridges. Width 5.5 Meters and span is  ranging from 6 Meters to 30 Meters.
uProject Cost             :-  GBP 100 mn
uSource of Funds      :-  ECGD, /Deutsche
uMain Contractor     :-  M/S. Cleveland Bridge Uk Ltd.
uEffective Date          :-  09-12-2014
uCompletion Date    :-  08-12-2017
Rural Bridges Project-Phase-III(463 Nos)
uScope of Work   :- Design and build of 463 Nos of bridges. Width 5.5 Meters and span is  ranging from 6 Meters to 30 Meters.
uProject Cost             :-  Euro 105 mn
uSource of Funds      :-  ATRADIUS/Netherland/Rabobank
uMain Contractor     :-  M/S. Janson Bridging International,BV
uEffective Date          :-  31-12-2014
uCompletion Date    :-  30-12-2017








































Comments

Popular posts from this blog

List of feasible Bridges

The following Bridges that can be Constructed            Name of Bridge DS Division ’; Decision of Join   Feasibility Study Report f Join Feasibility        Study Report 01 Neguna Ala Bandepara near the Sutharma house   Ampara Can be constructed (Details annexed). 02 Uhana Valikagakolla B44 to Hemethrurawa Mamedura Ala Uhana   Can be constructed (Details annexed). 03 Uhana Hahadda Kosyaya Dhama Uhana Can be constructed   (Details annexed). 04 Panamadu Bakkiella Bridge I   Porativu Pattu Can be constructed (Details annexed). 05 Panamadu Bakkiella Bridge II Porativu Pattu Can be constructed (Details annexed).    06 Panamadu Bakkiella Bridge III Porativu Pattu ...

Issues related with Rural Bridges

Issues related with Rural Bridges u Turfing and side slope are not according to the standards. u No proper Approach road. u Signal lights have not been fixed where appropriate   to avoid accidents. u Thickness of the tail side of slab is not standard in most of the cases.

Pulliyadumadu bridge - 1657 Vavunativu PS

 Date Handed Over 02.11.2017 Agency       Vavunativu PS After Before